Gulf South Pipeline Submits Application for Coastal Bend Header Project

Baker Hughes

The Federal Energy Regulatory Commission (FERC) on July 2 published in the Federal Register notice of the application by Gulf South Pipeline Company for a certificate of convenience and necessity for the Coastal Bend Header project in southeast Texas.

In its June 12 application to FERC, Gulf South Pipeline requested authorization to construction, own and operate new pipeline in Wharton and Brazoria counties, Texas; a new gas-fired compressor station in Wharton County; and certain interconnects. The project would deliver natural gas to the Freeport LNG liquefaction terminal, which is currently under construction.

Gulf South Pipeline said in its application that the total estimated cost for the project is $690 million, and the project needs to be in service in April 2018 to accommodate shipping agreements.

According to the application, Gulf South Pipeline plans to build 66 miles of 36-inch diameter pipeline and install two Solar Taurus 70 turbines and three Solar Titan 130 turbines with a combined horsepower rating of 83,597 for the compressor station. The project includes seven new interconnects with various interstate and intrastate pipelines, including a Gulf South Pipeline interconnect at the Coastal Bend Header. Gulf South Pipeline estimated that the pipeline, compressor station and interconnects would cost $545m.

The company said that the project also requires additions and modifications to certain portions of its legacy system, including:

  • Construction and operation of the new Brazos compressor station in Fort Bend County, Texas, consisting of a 26,400 horsepower electric motor- driven facility
  • Construction and operation of the new North Houston compressor station in Harris County, Texas, consisting of a 10,700 horsepower electric motor- driven facility
  • Modifications to the existing Goodrich compressor station in Polk County, Texas, consisting of piping modifications to allow for station flow reversal from north to south
  • Modifications to the former Magasco compressor station in Sabine County, Texas, consisting of modifications at the former station to allow for station flow reversal from north to south and the installation of one 15,748 horsepower Solar Mars 100 turbine

Gulf South Pipeline estimated that the total cost for the legacy system expansion would be about $145 million.

According to the application, the Coastal Bend Header project will create approximately 1.42 billion cubic feet per day (Bcf/d) of new pipeline capacity and 1.4 Bcf/d of new capacity on Gulf South Pipeline’s legacy system.

In 2013, Freeport LNG received DOE authorization to export up to the equivalent of 511 Bcf/year of LNG to non-FTA countries and a second authorization to export an additional 146 Bcf/year of LNG equivalent to non-FTA countries. FERC last July approved the expansion of the Freeport LNG facility for liquefaction operations and export. Freeport LNG started construction of the liquefaction project in November 2014 and expects to achieve commercial operation of the first liquefaction train in 2018.

Gulf South Pipeline said that the Coastal Bend Header project is supported by binding precedent agreements with four customers for 1.42 Bcf/d of capacity on the Coastal Bend Header and 1.4 Bcf/d on Gulf South’s existing legacy system under long-term, firm transportation contracts having a minimum term of 20 years.

Author Profile
jennifer delony
Managing Editor
LNG
ADIPEC


BOEM Issues Record of Decision for Western Gulf of Mexico Planning Area Lease Sale


Three Bottom-line Building Ways 3D Printing is Quietly Revolutionizing the Oil and Gas Industry


Waters of the U.S. Rule Affects O&G Industries ‘Almost from Top to Bottom’


Why Big Data in M&A Doesn’t Work


Why Your Dedicated Employees are Your Worst Enemy


RRC’s Porter Testifies on Oil Export Ban


Safety Offshore: Halliburton Diver Servicing a Blowout Off the Coast of Louisiana Early 1950s


Stellar Amenities: Halliburton Workers Prepare a Well Deserved Meal Early 1950s


Magnolia LNG, Meridian LNG Sign Capacity Agreement


Developing Technology: Humble Oil (Standard Oil) Offshore Rig 1950s


Railroad Administration Releases Rule on Unattended Trains


Texas Allocates $4.47M to Seismic Monitoring Program


Nothing Moves Without Energy!


Oklahoma Regulators Expand ‘areas of interest’ for Disposal Well Directive


Gulf South Pipeline Submits Application for Coastal Bend Header Project


DOE Grants G2 LNG Authority to Export to Countries with U.S. Free Trade Agreements


Severe Flooding Led to ‘significant downtime’ at Mid-Con Properties in 2Q15


API: Proposed rule ‘could make offshore operations less safe’


Energy Scene: Oil Patch BBQs


Transportation & Logistics History: J.M. English Trucking Company Early 1930s


Rules and Standards


America Resources Acquires Interest in East Texas Wells


Iran Agreement is Two-headed Monster


Industry Reacts to EPA Actions


FERC Begins Environmental Review of Four Texas Liquefaction Projects


Texas Oil and Gas Association Promotes Resources That Improve Oilfield Safety, Save Lives at 2015 Houston Oilfield Expo


Oilman Cartoon – September/October 2015


Q&A with Jason Spiess: Brian Lash – Target Logistics


The Original Oilmen: Glenn McCarthy and Michel T. Halbouty Early 1930s


Targeted Training with the LWCC Mobile Safety Training Center: Customer Testimony


Oil & Gas History: Texas Iron Works Early 1930s


Take A Bow


How to Thrive as an Exhibitor in the Face of Low Oil Prices


Senate Committee Unveils Energy Policy Modernization Act


A Family Company Dedicated to the Industry


FERC to Prepare EA for San Elizario Crossing Project

E-Fuels
Expo