Well No. 9

Implementing Artificial Gas Lift Earlier Can Improve Declining Wells

How an innovative approach regarding the optimum time to implement artificial gas lift has significantly improved production as wells decline – beginning on day one

Even after the prep work is finished and product recovery has been initiated, there is still no surefire way for oilfield exploration and production companies to confidently know how much and for how long their wells will produce recoverable oil and natural gas. There’s a simple reason for that: no two wells, even if they are located yards from each other, possess the same production and life cycle characteristics.

While this uncertainty can be frustrating for oilfield operators who must show their investors what their capital investment is actually buying them, it does create some opportunities. Namely, the opportunity for oilfield engineers to employ outside-the-box thinking when identifying ways to flatten each well’s inevitable decline curve, which will result in predictable production rates and higher monetary returns over a longer period of time.

Surveying the Field

A United States-based energy company operates wells in Texas’ Permian Basin, specifically Pecos County in the Southern Delaware Basin’s Wolfcamp A and Wolfcamp B formations. Most of the drilling sites are horizontally fractured wells with depths between 9,500 and 10,500 feet with FBHP (flowing bottom-hole pressures) from 5,000 to 6,000 psi. On average, each well has 50 fracking stages and requires 2,250-2,500 pounds of sand per foot and 60-80 barrels of water per foot.

The wells generally have strong bottom-hole pressures, but fail to flow naturally for an extended period of time. This means that they will require some form of flow-optimizing artificial lift earlier in their operational window. For example, the characteristics of Southern Delaware wells are such that they may only flow for 90 to 120 days before needing artificial lift, while wells located a handful of miles away may flow for more than two years before requiring intervention.

The most effective artificial lift system in this area has been one that features an ESP (electrical submersible pump) installed in the well. However, this approach can be problematic for three reasons:

  • Remote areas of West Texas do not always have access to reliable electricity.
    • If power is not readily available, building out a power grid can cost millions of dollars.
  • Alternative high-volume lifts that require a natural gas generator to convert natural gas into electricity can be rented, but this adds significant cost to the bottom line of the operator’s LOE (Lease Operating Expenses).
  • Other forms of artificial lift can have upfront costs of 10 to 20 times more than a set of gas lift valves.

For a potential solution, the producer reached out to Apergy, a leading provider of artificial lift technologies, to help oil and gas production companies optimize their returns safely and efficiently. The main request was a challenging one: Draw as much oil and natural gas out of the well as possible in the first 90 days of operation, while reducing LOE over the well’s production life cycle.

Seeing is Believing

The client was not averse to using costly alternative lifts if reaching the goal of maximized production rates could be realized, but Apergy’s oilfield engineers knew there had to be a more cost-effective way to attack the problem. So, they developed a four-pronged approach to introducing gas lift to a series of 10 Wolfcamp A and B wells.

The trial involved introducing to the wells at four specific points during their lifetimes a gas lift system that featured annular gas injection:

  • Option A: Well flows for 90 days before Annular Gas Lift is installed.
  • Option B: Well flows for 15-45 days before Annular Gas Lift is installed.
  • Option C: Annular Gas Lift is installed on the first day the well begins flowing.
  • Option D: Annular Gas Lift is installed on the first day the well begins flowing, while injecting gas in the first few days of production.

The first two options were not a radical departure from accepted norms. Options C and D, on the other hand, are solutions that few production companies will consciously choose to implement.

Let’s take a look at the performance of the 10 individual wells that were tested, one well with Option A, the next three with Option B, three with Option C and the final three with Option D (the production graphs for all wells are not shown because of space constraints):

Well No. 1 began producing in February 2017, but by the end of April was beginning to experience daily production declines, though water-recovery rates remained steady. Staying on the existing course could mean an early death for the well, but when Annular Gas Lift was installed at the 90-day mark, the production curve bumped up and remained steady, save for some small peaks and valleys, through June 2018.

Well Nos. 2 and 3 were a similar story to Well No. 1: strong early production that tapered off before the 90-day mark, when Annular Gas Lift was installed, which stabilized production. Annular Gas Lift valves were installed after only 15-45 days of operation. The result was a more gradual decline in production rates over the following months of operation. In fact, the wells’ returns beat the engineer’s forecast by such a wide margin that they were used as an example shown to investors of how ROI could improve with this well setup.

The wells using Option C were the results the engineers were really anxious to see since the setup – the Annular Gas Lift application deployed from the first day of the wells’ operation – was a departure from accepted norms. All three wells began operating in 2018 and the results have been similar – strong production rates from day one that have continued with only small valleys experienced. If there has been one standout performer, it has been Well No. 7, which showed an absolutely negligible decline curve over its first three months of operation.

The last wells had Annular Gas Lift valves installed with injected gas within the first few days of flowing. The return has been so impressive, the decline curve so negligible and the LOE so optimized that the operator has decided to treat all future wells in the Southern Delaware Basin in this fashion.

Several takeaways can be analyzed when considering how these wells performed based on the four different gas lift setups:

  • Adding a velocity string during flowback reduced slugging and outproduced casing flow.
  • Switching from Annular Gas Lift to Conventional Gas Lift did not improve production at 2,500 b/d total fluids.
  • When the injection gas was turned off after the first 90 days, the wells loaded up immediately.
  • Production results compared to other forms of high-volume lift were similar and, in some cases, surpassed due to lack of downtime, but at a fraction of the cost.

Conclusion

In an industry like oil and gas exploration and production that features so many well-to-well variables that must be considered when determining the best way to produce the well, there is simply no one-size-fits-all solution. While many companies continue to rely on alternative high-volume lifts – or wait to introduce artificial lift systems until the last moment before the well loads up – forward-thinking companies are finding that there are some noteworthy alternatives available. Based on the empirical information noted above, one of the more successful approaches is intentionally installing an artificial lift system earlier in the well’s life, up to and including the first day of operation, with the results so far speaking for themselves.

Well No. 1Well No. 2Well No. 3Well No. 5Well No. 7Well No. 8Well No. 9
Author Profile
Regional Operations Manager - 

Andrew Poerschke is the Regional Operations Manager for Apergy, Houston, TX, and can be reached atandrew.poerschke@apergy.com.

Author Profile
Lead Completions Engineer - 
Author Profile
Senior Production Engineer - 
3 Ways Technology is Going to Shape the Oil and Gas Industry Free to Download Today

Oil and gas operations are commonly found in remote locations far from company headquarters. Now, it's possible to monitor pump operations, collate and analyze seismic data, and track employees around the world from almost anywhere. Whether employees are in the office or in the field, the internet and related applications enable a greater multidirectional flow of information – and control – than ever before.

Related posts