Energies Media
  • Magazine
    • Energies Media Magazine
    • Oilman Magazine
    • Oilwoman Magazine
    • Energies Magazine
  • Upstream
  • Midstream
  • Downstream
  • Renewable
    • Solar
    • Wind
    • Hydrogen
    • Nuclear
  • People
  • Events
  • Subscribe
  • Advertise
  • Contact
    • About Us
No Result
View All Result
No Result
View All Result
Energies Media
No Result
View All Result

FERC moves forward with environmental assessment of the South System Expansion 4 pipeline

by Kyle
March 24, 2026
FERC South System Expansion 4 pipeline

Credits: Selim Arda Eryilmaz

Gastech

Most expansions in pipelines progress sequentially as each review progressively narrows down uncertainty and defines what is ultimately buildable. One of the most critical of the various stages of progressive narrowing of uncertainty is the completion of an environmental assessment or an impact statement at the federal level, and this is where Kinder Morgan’s South System Expansion 4 (SSE4) pipeline project has progressed to.

A critical review stage enters public view

Late in January 2026, Staff members at the Federal Energy Regulatory Commission (FERC), the U.S. federal government’s primary energy regulator, released a Draft Environmental Impact Statement (DEIS) that encompasses both the South System Expansion 4 project and the Mississippi Crossing pipeline project.

This release of the DEIS formally moves SSE4 through the review process required by the National Environmental Policy Act (NEPA) and allows interested parties to make comments prior to the issuance of any permit. A draft Environmental Impact Statement does not constitute an approval.

Kinder Morgan phase 4 expansion

Kinder Morgan progresses Phase 4 expansion to increase capacity on its South System pipeline network

March 23, 2026
Kinder morgan conversion work hiland express

Kinder Morgan progresses with conversion work on the Hiland Express pipeline system

March 22, 2026
Kinder Morgan advances expansion

Kinder Morgan advances expansion work on the Gulf Coast Express natural gas pipeline

March 21, 2026

Rather, the draft EIS is FERC’s initial analysis of potential environmental impacts associated with the construction and operation of the proposed facilities. All interested parties are invited to submit comments; the current comment deadline is set for March 23, 2026.

What does the environmental assessment cover?

The South System Expansion 4 project is being developed by Southern Natural Gas Company and Elba Express Company, two Kinder Morgan subsidiaries. As described in the Draft Environmental Impact Statement, SSE4 would require the construction of several pipeline loops running in parallel to existing pipeline infrastructure across Mississippi, Alabama, and Georgia, along with upgrades to existing compressor stations and metering facilities.

The project is intended to increase the daily transportation capacity of the south main line system by approximately 1.3 billion cubic feet per day. Much of the work would take place on or adjacent to existing pipeline rights-of-way. Therefore, this is an example of a “brown field” approach and will result in significantly less new land being disturbed than would be necessary if entirely new corridors were built.

The Draft Environmental Impact Statement assesses numerous elements of the project, including but not limited to:

  • Land use
  • Water resources
  • Wildlife habitats
  • Air quality
  • Potential cumulative impacts.

The document also evaluates alternative scenarios and possible mitigation measures that could be implemented if the project is approved.

Why this step matters for project timing

The issuance of the Draft Environmental Impact Statement is one of the last major analytical steps that FERC must complete before issuing its final order on the project. In addition, SSE4 has been designated a FAST-41 covered project, and therefore, all federal agencies are working under a coordinated permitting schedule with published deadlines.

According to FERC’s current permitting schedule, the Final EIS is expected to be completed by the end of June 2026. Assuming the review process remains on track, a certificate order approving the project could be issued by July 31, 2026. While the dates provided represent a likely timeline for the issuance of the Final EIS and certificate orders, they are not guaranteed. However, these dates will provide much-needed clarity regarding the time frame when regulatory uncertainty may begin to dissipate.

A procedural milestone with strategic implications

While the environmental review process may seem like simply a matter of procedure, it frequently determines whether a project can transition from planning to execution. FERC’s decision to proceed with the environmental review of the South System Expansion 4 pipeline represents a pivotal moment in the project’s development. Although no final decision has yet been made, the issuance of the Draft EIS clearly brings the proposal into sharper focus and indicates that SSE4 is rapidly approaching the final stages of federal review.

Author Profile
Kyle
Author Articles
  • Kyle
    ExxonMobil board proposes relocating corporate domicile to Texas to reinforce domestic upstream strategy
  • Kyle
    Suncor advances refinery upgrade initiatives aimed at boosting product yields across its Canadian operations
  • Kyle
    Kinder Morgan progresses Phase 4 expansion to increase capacity on its South System pipeline network
  • Kyle
    BLM initiates formal protest window ahead of Utah oil and gas lease auction scheduled for March 31, 2026
  • Kyle
    Marathon Petroleum receives ENERGY STAR distinction for operational efficiency at refining facilities
  • Kyle
    Kinder Morgan progresses with conversion work on the Hiland Express pipeline system
WUC

Energies Media Winter 2026

ENERGIES (Winter 2026)

IN THIS ISSUE


Kellie Macpherson, Executive VP of Compliance & Security at Radian Generation


The Importance of Innovation in LWD Technologies: Driving Formation Insights and Delivering Value


Energies Cartoon (Winter 2026)


Why Lifecycle Thinking Matters In FPSO Operations


The Vendor Trap: How Oil And Gas Operators Can Build Platforms That Scale Without Losing Control


Letter from the Editor-in-Chief (Winter 2026)


Protecting Critical Infrastructure and Operations in the Digital Age


Pumping Precision: Solving Produced Water Challenges with Progressive Cavity Pump Technology


Infrastructural Diplomacy: How MOUs Are Rewiring Global Energy Cooperation


The Duality of Landman’s Andy Garcia

Gastech
WUC
  • Terms
  • Privacy

© 2026 by Energies Media

No Result
View All Result
  • Magazine
    • Energies Media Magazine
    • Oilman Magazine
    • Oilwoman Magazine
    • Energies Magazine
  • Upstream
  • Midstream
  • Downstream
  • Renewable
    • Solar
    • Wind
    • Hydrogen
    • Nuclear
  • People
  • Events
  • Subscribe
  • Advertise
  • Contact
    • About Us

© 2026 by Energies Media