Wind

A German offshore wind farm stood up 22 of its 44 machines between June and the end of August, and the other half has to go in during the months the first half was scheduled to avoid

By Hugo Rojas · September 17, 2026 · 2:50 PM · 5 min read
First turbine installation at Nordseecluster A offshore wind farm in the North Sea, offshore giants rising

A quay on the Ems estuary in the northern Netherlands, stacked with steel.

Tower sections stand on end in rows. Nacelles sit under covers. Blades lie in cradles.

None of it is in Germany, and all of it is bound for a German wind farm.

So the work offshore can only run as fast as the yard onshore hands pieces over, and a vessel waiting at a berth costs the same as a vessel waiting on weather.

A vessel loads here, then sails roughly 31 miles past the last German island.

Twenty two machines went up that way by August.

Twenty two more have not.

Why the loading quay sets the pace and not the sea

A modern offshore turbine does not travel as a turbine. It travels as a set of parts.

One tower in sections, one nacelle, three blades, and every piece too large for an ordinary cargo berth.

The quay has to carry the point loads. The water alongside has to be deep enough for a jack up hull. The yard behind has to hold components until the vessel asks for them.

Few ports on this coast do all three at once, which is why the base for this project sits across a national border rather than on the German coast it serves.

So the work offshore can only run as fast as the yard onshore hands pieces over, and a vessel waiting at a berth costs the same as a vessel waiting on weather.

The lift happens at sea. The bottleneck sits on land.

What is standing in the water right now

Forty four turbines are planned for this first phase, each rated at up to 15 megawatts.

Half of them were in place at the end of August, which the developer confirmed in its own statement.

Hub height is about 476 feet above the waterline, and a single blade measures about 377 feet from root to tip.

The first machine went up in the middle of June. Current from the array reached the grid at the end of July, six weeks later.

Together the 44 will be rated at 660 megawatts, the opening phase of a cluster planned to reach 1.6 gigawatts once a second stage follows later this decade.

Ownership sits with a German utility holding just over half and a Norwegian fund holding the rest, which matters mainly because it fixes who carries a delay.

Eleven weeks produced half an array and first power.

The part of the calendar that stays out of the announcements

Here is where a halfway mark stops being reassuring.

Those 22 machines went in across June, July and August, which is the calmest stretch of the year in this corner of the North Sea.

The remaining 22 are due before the end of the year, and October through December is emphatically not that stretch.

Wave height decides whether a jack up can position and lift its hull clear of the water at all.

Wind limits for flying a single blade onto a hub are tighter than for almost any other operation the vessel performs, because a blade is a sail until the last bolt is in.

The same count twice over is not the same job.

What the gaps between machines actually buy

A line that turns up often in coverage holds that turbines are set far enough apart for one rotor’s wake to disappear before it reaches the next.

That is not what spacing does.

Wake losses inside a large offshore array are real, routinely measured and permanent. Layout is a compromise between cable length, lease boundary and lost output, settled long before anyone goes to sea.

Designers reduce the loss. They never remove it, and the machines downwind inside any big farm see slower, rougher air than the front row does.

A neighboring German project weighed the same tradeoff before setting 64 machines without state subsidy behind them.

The halfway count and the installation dates are set out by the developer.

Spacing buys less loss, never no loss.

What has to happen after the last blade goes on

Full grid connection is targeted for early next year, and that is a separate milestone from the last machine standing.

Between the two sits commissioning, which is where a fleet of new turbines finds its faults, one converter and one pitch system at a time.

An array with every tower in place still earns nothing until the collection platforms and the export route are live and accepted.

A second phase of 900 megawatts is scheduled for installation in 2028, on the same seabed and out of the same yard, with operation expected early in 2029.

The output claimed for the finished cluster is about 6.5 terawatt hours a year, and the developer presents that figure as supply aimed at industrial users rather than at households.

The platforms that gather and step up the output were staged in a campaign of their own, covered under the substations.

The vessel, the load size and the June lift are reported by a wind title.

Half the wind farm is standing, and the harder half begins next month in worse weather.

Author Profile
Editor

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.

Hugo Rojas
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.

Hugo_writer
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.