Poland and Westinghouse launch long-lead component procurement for country’s first nuclear power plant, targeting 2036 startup

On October 8, 2026, Poland’s state nuclear company PEJ formally commissioned Westinghouse Electric Company to begin procuring long-lead items for the first AP1000 reactor unit at the Lubiatowo-Kopalino nuclear power plant. Officials called it one of the most important milestones in preparing for construction — with the goal of delivering electricity from the plant’s first reactor by 2036.
PEJ commissions Westinghouse to procure nuclear island Components
The October 8 commission covers six key components of the nuclear island, with the reactor containment vessel and its structural modules at the center of the scope. These rank among the most technically demanding parts of any AP1000 build, requiring specialized suppliers and years of coordinated production to get right.
The timing connects directly to a deal struck just weeks earlier. In September 2026, PEJ and the Westinghouse-Bechtel consortium reached agreement on the main commercial terms of the EPC contract — and that progress cleared the way for this next step.
Dan Lipman, President of Global Business Initiatives at Westinghouse Nuclear, framed Polish industrial participation as something bigger than a single project.
Bechtel had already received an earlier LLI order covering the components under its responsibility. This latest commission specifically addresses Westinghouse’s portion: the nuclear island in the broadest sense. Together, the two orders now cover the full LLI scope across the consortium.
Why long-lead procurement must begin years before construction
Long-lead items aren’t called that by accident. These components are among the most technologically complex in any nuclear project, and getting them from design to delivery can take many years. Specialized manufacturers operate at limited global capacity, so securing a spot in their production queue early isn’t optional — it’s essential.
Starting now gives PEJ and the consortium room to breathe during EPC contract negotiations. As Marek Woszczyk, President of PEJ’s Management Board, explained, the goal was to avoid delays in finalizing the contract putting the construction schedule at risk. Ordering LLIs early removes that pressure.
Budget control is another reason to move quickly. The components covered by these orders represent a significant share of total project costs, and locking in procurement timelines well in advance gives the project team better visibility into future expenditures — along with more leverage in managing them. Early LLI procurement is standard practice in nuclear projects worldwide. Poland isn’t reinventing the wheel; it’s following a well-established playbook used to keep complex builds on track.
Scope of work and role of Polish industry
The procurement process Westinghouse is now executing involves more than simply placing orders. The scope includes preparing technical documentation, developing quality and supervision plans, selecting and contracting suppliers, and placing material orders to kick off production. Delivery of the finished components to the Lubiatowo-Kopalino construction site will happen later, under a separate order PEJ plans to issue as part of the full EPC contract. The current phase is about getting production started.
Polish companies could play a meaningful role in this supply chain, but there’s a condition. To bid for contracts on the most specialized work, they’ll need to obtain ASME NQA-1 certification — the international nuclear quality standard the industry requires at this level. That process takes time and real investment.
Dan Lipman, President of Global Business Initiatives at Westinghouse Nuclear, framed Polish industrial participation as something bigger than a single project. He described it as a critical first step for Polish companies to supply nuclear-grade components — not just for Lubiatowo-Kopalino, but for future AP1000 projects across Europe. Qualifying now could open doors well beyond their own country’s first reactor.
Project timeline, energy policy context, and next steps
The 2036 commissioning target for the first unit at Lubiatowo-Kopalino isn’t just a project milestone — it’s a national policy commitment. Poland’s Ministry of Climate and Environment has positioned the plant as a cornerstone of the country’s energy security strategy, providing a stable, zero-emission power source for decades to come.
Deputy Climate Minister Miłosz Motyka put it plainly: the goal is for electricity from the first reactor to reach consumers in 2036. That framing reflects how central the project is to Poland’s broader energy transition as the country works to reduce its dependence on coal.
The current LLI procurement falls under the Engineering Development Agreement already in place between PEJ and the Westinghouse-Bechtel consortium — the framework governing preparatory work while the full EPC contract is negotiated in detail. Full construction will begin once those negotiations conclude, and all preparatory steps are complete. The LLI orders are designed specifically to ensure that when construction does start, the most time-sensitive components are already in production and won’t become a bottleneck.
What this milestone means for Poland’s nuclear future
Poland has now taken two concrete procurement steps — one for Bechtel’s scope, one for Westinghouse’s — that together signal the project is moving from planning into execution. The September commercial agreement, followed by this October commission, reflects a deliberate sequencing strategy: lock in the big-picture terms, then start the clock on the parts that take longest to build.
The 2036 target remains ambitious, and detailed EPC contract negotiations still lie ahead. By beginning LLI procurement now, though, PEJ and the Westinghouse-Bechtel consortium have bought themselves the scheduling flexibility needed to finalize those negotiations without sacrificing the timeline. For a country building its first nuclear power plant, that kind of discipline in early-stage project management may prove to be one of the most consequential decisions made along the way.
Kelly is an experienced writer with 15 years of experience exploring the big stories that shape our world, from tech breakthroughs and space exploration to climate, energy, and the fascinating quirks of science. She has a talent for turning complex ideas into sharp, memorable insights that stay with readers long after they’ve finished reading.