Nuclear

Ontario’s Darlington nuclear plant completes decade-long rebuild, replacing 1,920 fuel channels and 3,840 feeder pipes

By Lindi Miti · November 27, 2026 · 2:40 PM · 4 min read
Ontario’s Darlington nuclear plant completes decade-long rebuild Darlington Nuclear Generating Station in 2022 - Robert T Bell from Oshawa, Canada - IMG_7476 (https://commons.wikimedia.org/wiki/File:Darlington_Nuclear_Generating_Station_IMG_7476_(cropped).jpg) - CC BY 2.0

Refurbishing a major nuclear plant unit by unit requires meticulous attention to detail and may take over a decade.

When anticipating such a huge project, much like construction, many expect it to run over time and over budget.

However, OPG’s Unit 4 Darlington Refurbishment reached completion four months before schedule and over a hundred million dollars under budget.

Through this project, we have demonstrated to the world that complex nuclear projects can be completed successfully, ahead of schedule and under budget,

How did OPG manage to replace thousands of core reactor parts while beating schedule and budget targets?

How OPG refurbished four reactors at the Darlington Nuclear Generating Station one unit at a time

A little over ten years ago, Ontario Power Generation (OPG) set out to complete the Darlington Refurbishment project.

The Darlington Nuclear Generating Station is a four-unit nuclear plant located on the north shore of Lake Ontario in Canada.

The nuclear plant took almost a decade to build, beginning in 1981 and finally reaching operation in 1990.

Nuclear plants can run for decades without major interruptions.

However, at the thirty-year mark, nuclear reactors will need to be refurbished to keep running safely.

So in October 2016, OPG started refurbishing all four reactors at the Darlington Nuclear Generating Station in Ontario, one unit at a time.

First, they started with Unit 2, then Unit 3 followed. Then, they circled back to Unit 1, before finally getting started with Unit 4 in July 2023.

OPG started working on Unit 4 and finished it within 968 days.

Why keeping Darlington running mattered for steady, low-carbon electricity in Ontario

Reburbishing the Darlington nuclear plant will secure 3,512 megawatts for another 30 more years for Ontario.

That means for the next three decades, the Darlington nuclear plant guarantees employment for maintenance and operations staff.

In addition to that, the refurbishment project provided an additional 2,000 direct jobs annually, primarily made up of contractors.

All the labor was sourced from local skilled labour in the region. And a total of over 6000 workers helped to make the project a success.

When it comes to economic benefits to Ontario, the refurbishment alone is projected to generate $14.9 billion.

Over time, considering another 30 more years of station operations, the project is projected to generate substantial economic benefits for Ontario.

Ultimately, total economic output from the plant is estimated to reach $89.9 billion.

How crews replaced 960 feeder tubes and 480 fuel channels per unit

OPG finished the ten-year-long refurbishment four months ahead of schedule and $150 million under budget.

Working with one nuclear reactor unit at a time, they started the process by shutting down each nuclear reactor.

Then, they defueled each reactor by draining out the heavy water.

They replaced 960 feeder tubes and 480 fuel channels per unit.

That makes the total number 1,920 fuel channels and 3,840 feeder pipes across all four units.

Today, Unit 4 at Darlington Nuclear Generating Station has been reconnected to the grid at 100% power.

It is generating low-carbon, reliable power for Ontario for the first time since it was shut down in July 2023.

For the next thirty years, the continued operation of the nuclear plant will prevent 297 megatonnes of greenhouse gas emissions.

That figure is the same as removing two million passenger vehicles from the road.

Long-term clean energy for the next three decades in Ontario

OPG employed thousands of workers to refurbish the Darlington Nuclear Generating Station.

Their diligence and skills ensured that the project was completed four months ahead of schedule and delivered way under budget.

Nicolle Butcher, OPG’s President and CEO. gave thanks to all who made the Darlington Refurbishment a resounding success.

“Through this project, we have demonstrated to the world that complex nuclear projects can be completed successfully, ahead of schedule and under budget,” said Butcher. Now Ontario can look forward to long-term clean energy for the next three decades.

Lindi Miti
Lindi Miti

Lindi is a copywriter and marketing professional with over 10 years of experience across finance, fintech, luxury lifestyle, and renewable energy. She writes with a keen interest in the business and innovation shaping the energy transition.

Lindi writer
Lindi Miti

Lindi is a copywriter and marketing professional with over 10 years of experience across finance, fintech, luxury lifestyle, and renewable energy. She writes with a keen interest in the business and innovation shaping the energy transition.