Eleven turbines keep turning off Aberdeen Bay past a decade of legal fights launched from a nearby golf resort, and they still generate power today

By Hugo Rojas · October 29, 2026 · 10:50 AM · 5 min read
Eleven turbines off Aberdeen Bay near a golf course coastline, eleven turbines keep

A golfer lines up a drive on the Scottish coast.

Behind the green, eleven white towers turn slowly against the gray water of Aberdeen Bay.

They have stood there since 2018.

They have not moved, and barring a reversal nobody has filed for, they are likely to keep turning past the resort’s next anniversary and the one after that.

The demonstration wind farm was never supposed to become a landmark of anything except engineering.

Instead it became the backdrop to one of the longest fights in modern offshore wind, one a former American president tried for years to win.

It never worked, so what actually kept the turbines standing through all of it?

Why the turbines survived every legal challenge thrown at them

The project, officially the European Offshore Wind Deployment Centre, sits roughly a mile and a half off Blackdog, within sight of a golf resort built on the Menie Estate north of Aberdeen. When the developer finalized plans for eleven turbines in the bay, the resort’s owner argued the view itself was a protected scenic asset and fought the consent through Scotland’s courts.

That argument eventually reached the country’s highest court, which rejected it unanimously, ruling that the Scottish government’s consent for the turbines stood. The legal theory, that a sea view from a golf resort could block a licensed energy project, did not survive contact with the actual permitting law.

So the turbines went up anyway, on schedule. The resort’s owner has kept raising the issue in public for a decade since, most recently calling for the turbines to come down the same week he praised a new oil and gas drilling approval in the North Sea.

What eleven turbines in a tidal bay actually had to prove

This was never meant to be a commercial wind farm in the usual sense. It was built as a test bed, a place for manufacturers to prove new turbine and foundation designs in real seawater before committing them to much larger projects further offshore.

Eleven machines is a small fleet by today’s standards, where new arrays routinely carry a hundred or more. What made the site useful was not scale but conditions, since Aberdeen Bay sees strong tidal currents, shifting sand, and the kind of short, steep North Sea chop that punishes a weak foundation design quickly.

Engineers wanted a site hard enough to expose flaws fast, and this bay delivered that in abundance.

How the project actually got built, turbine by turbine

Several of the turbines were seated on suction bucket foundations, a technique that uses pressure differences to pull a hollow steel cylinder into the seabed instead of pile driving it in. It was an unusual choice for a UK offshore project at the time, and it worked well enough that the technique has since spread to other sites.

Construction moved in stages. The first foundation went into the seabed in March 2018, and the first turbine followed the next month, with the eleventh and final machine erected by the end of May, completing the array in under three months once installation began in earnest.

Power comes ashore through more than four miles of underground cable running from a substation at Blackdog to the grid connection point at Dyce, on the edge of Aberdeen. The turbines use 66 kilovolt sea cables, a voltage level that has since become standard for medium sized offshore arrays.

None of that infrastructure is visible from the fairway. What golfers see is simply the towers, turning in a bay that was fished and sailed long before anyone proposed putting machinery in it.

The fight that keeps resurfacing even after the ruling

The legal question was settled in 2015, yet the public argument never really stopped. The disagreement escalated years earlier into a feud between the resort’s owner and Scotland’s then First Minister, and it has resurfaced periodically ever since.

The latest flashpoint came this past week, when the resort’s owner, now serving as US president, posted a demand to remove the turbines while welcoming approval of a separate North Sea gas field near Aberdeen. One local energy official noted at the time that the ruling had already settled the matter, and that nothing since had changed it.

It was the same argument made a decade earlier, repeated almost word for word. The machines it targets have spent most of that decade generating electricity without interruption, which is not every offshore project’s experience, as the political resistance seen elsewhere in Europe shows.

What a small test site in a contested bay still has to teach

Eleven turbines will never be mistaken for a flagship wind farm. But demonstration sites like this one exist precisely to take the hits a larger commercial project cannot afford to absorb, including the foundation failures and cable route problems that only show up after years at sea.

That same logic now shapes how operators think about running turbines for decades rather than years. Some developers have found that producing less power at certain moments extends a turbine’s working life well beyond its original design window, a lesson learned partly from early test arrays like this one.

The bay’s turbines have now outlasted the legal campaign against them by more than a decade, which is its own kind of verdict. They have not moved, and barring a reversal nobody has filed for, they are likely to keep turning past the resort’s next anniversary and the one after that.

Hugo Rojas
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.

Hugo_writer
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.