Crews installed 12 turbines at Sweden’s Ljungbyholm wind farm in 35 winter days despite snowstorms and temperatures as low as 5°F
A construction site can be a tough place to work in winter. The snow covers the ground, the cold tests the equipment, and every lift calls for careful coordination.
But one particularly harsh winter saw the Ljungbyholm wind farm near Kalmar, in south-eastern Sweden, reach a major construction milestone.
Wind projects are already complex, involving careful engineering and scheduling, but winter adds another layer of complexity. At Ljungbyholm, every step in the construction was a coordination test.
The wind farm is expected to generate 150 GWh annually and will add a considerable amount of generation capacity to Sweden’s renewable energy landscape.
What made it possible for the project to go ahead despite the bad weather?
The wind farm takes shape near Kalmar
The Ljungbyholm wind farm is located outside Kalmar municipality, in the southeast of Sweden. The project was a partnership between renewable energy developer OX2 and turbine manufacturer Nordex, which provided the equipment.
Nordex is a global manufacturer of onshore wind turbines and has over 40 years of experience in renewable energy.
The company, founded in 1985, became a leading international manufacturer after merging with Acciona Windpower in 2016. The company designs, builds, installs and services wind turbines and has more than 10,900 employees around the world.
Nordex develops turbine systems for different geographical and climatical conditions, currently focusing on machines in the 4 to 7 MW class.12 wind turbines will be required, using Nordex’s Delta4000 platform for the wind farm. Each turbine is mounted on a 125-meter-tall tower with 75-meter-long blades.
Before the turbines could generate electricity, crews had to physically install them, hook up the equipment, and begin commissioning.
The sequence becomes more complicated when winter conditions influence access, lifting operations, and movement of large components. Ljungbyholm was able to meet these challenges, and the project was on schedule.
Snow and freezing conditions tested
From installation to operation, commissioning a wind farm includes testing individual parts and ensuring that the turbine works correctly when the wind conditions change.
The control systems also need to speak to the equipment that tracks and manages the generation of electricity.
The first kilowatt-hour is an important transition from construction to electricity production. That shows the turbine is at the point where it can generate power. There may be some additional testing and commissioning before it’s fully online.
The installation period of the main turbines began in mid-January 2021.
The work was completed in 35 days, and Nordex said that around 100 people were working on site each day. The weather was far from normal. Temperatures dropped to 5 degrees Fahrenheit, and the area was covered with snow, well above its normal averages.
Heavy sections of equipment, the nacelle and rotor components must all be installed and accomplish the work needed before testing can start.
The site team continued to do well despite the freezing conditions, according to Nordex’s April 1, 2021 project update.
Winter conditions also require careful planning, taking into consideration daylight hours, access to the site, and changing conditions. These factors can impact how teams manage daily operations
35-day installation reaches first power milestone
The key achievement was that the installation work on all 12 machines was finished at the end of February and then, in the last week of March, each turbine produced its first kilowatt-hour of electricity, a significant move from construction to commissioning.
One coordinated outcome, twelve windmills
The wind farm is expected to generate 150 GWh annually and will add a considerable amount of generation capacity to Sweden’s renewable energy landscape. It also shows the value of careful planning and coordination in developing wind power infrastructure in harsh climates.
Ljungbyholm showed how a significant renewable energy project can move forward in harsh winter conditions. The first electricity generated from all 12 turbines was a big milestone, but commissioning had to continue.
How are developers tackling even bigger sites in harsh winter conditions?
Bronwyn has over 20 years of experience in media, digital publishing, and storytelling as a journalist, content creator, and publishing editor. She writes about various niches and has a keen interest in science, technology, energy, and innovation.