Nuclear

Deep Fission locks in a 25-year power deal for its Kansas project, giving the company’s underground nuclear concept a long-term customer before it comes online

By Prince Sibanda · October 26, 2026 · 6:30 AM · 4 min read
Deep Fission 25-year Kansas project

Now is the perfect opportunity for energy companies to capitalize and reach the most profitable agreements that will enable them to generate revenue for many decades to come. The United States has dedicated a tremendous focus to diversifying the energy portfolio of every state and ensuring that there is a consistent energy supply everywhere. This means the government, or the Department of Energy, is in a position where it needs to work with private companies rather than instilling unnecessary hurdles because those companies will ensure the nation reaches its targets. As of late, Deep Fission locked in a 25-year power deal for its Kansas project, giving the company’s underground nuclear concept a long-term customer before it comes online.

Assessing Deep Fission’s growing influence on the nuclear energy landscape

Deep Fission has been among the most active companies in 2026, but despite its success, the company is still looking to finish off the year on a high note. Deep Fission is currently developing technology that places a small modular pressurized water reactor in a borehole roughly one mile underground.

Because the nuclear energy sector is influenced by nuclear, Deep Fission is in a good position to be among the pioneers of nuclear generation for the next decades to come. The company’s Gravity Nuclear Reactor approach combines established pressurized water reactor technology with a novel underground deployment model designed to simplify construction, enhance safety, and support scalable commercial deployment.  

The finalized agreement binds Deep Fission to pursue the project and to supply power once licensed and operating, subject to the agreement’s terms and conditions.

Deep Fission is focused on delivering reliable, low-carbon baseload power to meet growing electricity demands from utilities, industrial customers, and data centers, which makes the company a worthy addition to the United States’ nuclear sector.

Attaining a long-term customer: Deep Fission locks in a 25-year power deal for its Kansas project

A press release from Deep Fission captured the attention of the energy industry as it announced that the company has reached a Master Energy Purchase Agreement with the Great Plains Development Authority (GPDA). This quasi-municipal entity owns the Great Plains Industrial Park in Parsons, Kansas. Although energy companies are competitive, they still closely analyze each other’s projects, hoping to apply the same or a similar blueprint to their approach.

The company converts the parties’ December 2025 letter of intent into a definitive contract for a commercial project at the site of Deep Fission’s Department of Energy (DOE) pilot. The Great Plains Industrial Park is known for providing large-scale, flexible environments located directly on the Union Pacific main line, designed to support advanced industry, testing, and innovation.

There is a strong belief that Great Plains is emerging as a premier destination for enterprises shaping the future of industry and technology. The finalized agreement binds Deep Fission to pursue the project and to supply power once licensed and operating, subject to the agreement’s terms and conditions. When two entities reach a long-term agreement, they are obligated to complement each other effectively.

Delving deeper into the terms agreed by Fission for the Kansas-based project

Under the agreement, GPDA will purchase electricity that is generated and made available by Deep Fission to satisfy the electricity demands of industrial park tenants, up to the contracted capacity, with no minimum purchase obligation.  

Additionally, the agreement also allows GPDA to assign its purchase obligations to qualifying tenants. The initial phase is predicted to be 150 MW with a target date of commercial operation on September 30, 2028, and grow through later phases to a total of 2,000 MW pending further demand growth.  

What does the agreement mean for Deep Fission moving forward?

Deep Fission is teeing itself up for a massive 2027 by reaching such a massive agreement toward the end of the year. The agreement is seen as turning a shared vision into a binding commitment between two entities that believe they are on the same page.

The Great Plains Industrial Park covers more than 14,000 acres in Labette County on the site of a former U.S. Army ammunition plant, with existing rail access, utilities, and space for large industrial users.

Prince Sibanda
Prince Sibanda

Prince is a versatile writer focused on energy, automotive, environmental, and general news topics. He makes complex technical and policy issues clear, engaging, and accessible for a broad audience.

Prince Writer
Prince Sibanda

Prince is a versatile writer focused on energy, automotive, environmental, and general news topics. He makes complex technical and policy issues clear, engaging, and accessible for a broad audience.