Wind

Poland took its first offshore wind power ashore in July from a Baltic farm 14 miles out with about 50 of 76 turbines standing, and the rotor on each sweeps more than 8 football fields

By Hugo Rojas · September 6, 2026 · 12:50 PM · 5 min read
An offshore wind turbine standing in the Baltic Sea Credits: Baltic Power

Fourteen miles out in the Baltic the water is cold and flat, and until this past July nothing under it carried electricity toward the Polish shore.

On a morning in early July a signal arrived at an onshore substation in the north. Nobody outside the control room saw it.

The grid operator confirmed receipt. The first offshore watts ever generated in the country had crossed the seabed and entered the national network.

That is enough for more than a million and a half households, and it amounts to roughly three percent of national electricity demand from a single site.

The farm that sent them is not finished yet.

Why the grid connection takes longer than the turbines

Electricity does not jump from a spinning rotor to a household socket. Between the two sits a chain of infrastructure that has to be completed in strict sequence.

Foundations go in first. Then array cables link turbine to turbine at sixty six kilovolts, an offshore substation collects that power and steps the voltage up, export cables run it to shore, and an onshore substation raises it again for the national network.

Each stage depends entirely on the one before it. A foundation has to be grouted and inspected before array crews can approach, and the offshore substation has to be energized and tested before a single watt travels the export route.

That sequencing logic is why cable burial begins months before the first turbine ever turns.

It is also why the milestone that gets reported is almost never the one that took the longest to reach. The cable came first.

What the hardware out there actually is

The farm is built around 76 turbines rated at fifteen megawatts each, for roughly twelve hundred megawatts in total. That is a large offshore wind plant by any European measure.

The rotor on one of these measures 774 feet across and sweeps close to eleven acres of air on every revolution. That is more than eight football fields, not the one that keeps getting printed.

The array occupies a lease zone of about 50 square miles, roughly fourteen miles from the nearest coastline, which keeps the whole thing below the visual horizon from the beach. Nothing of it is visible from shore.

Design life is put at around thirty years, which is the span over which all of this has to pay for itself.

The cable and the voltages it steps through

All the cable lines together run more than 217 miles, routed to avoid shipping lanes, sandbanks and protected seabed habitat.

That total covers the array cabling and the export route between them. Burial depth varies with the geology underneath, going deeper in softer sediment where trawl gear and anchors reach.

Offshore, the substation takes the array in at sixty six kilovolts and lifts it to 230 kilovolts for the run to land. Onshore it steps up again to 400 kilovolts for the transmission network.

Weather windows in the Baltic are narrow.

Cable laying crews typically work in bursts of favorable conditions measured in days, then wait out wind and swell before resuming, and getting the whole length buried on schedule took constant coordination between vessel operators, port logistics teams and the authority certifying each completed section.

The number the coverage keeps shrinking

At full output the farm is expected to generate 4 billion kilowatt hours a year. That is the plateau figure rather than the first year.

That is enough for more than a million and a half households, and it amounts to roughly three percent of national electricity demand from a single site.

Both of those figures get reported low, often as around a million homes. That understates the thing by half.

The scale is the point. Poland went into this decade with almost nothing offshore, and one project now covers a measurable slice of the whole country.

Independent coverage of first electricity put the same numbers on the record within days.

What first power was and what is still left

On the tenth of July the grid operator logged the connection. At that moment just over 50 of the seventy six turbines were standing.

The installation campaign was past eighty percent complete, with full commercial operation targeted for the second half of the year.

Reaching first power before the whole farm is up matters financially rather than symbolically. Every day of early generation feeds revenue against billions in debt financing, and lenders read early production as a proxy for how the rest of the schedule will go.

It also gives backers concrete evidence that the engineering chain holds end to end, from a foundation on the seabed through to onshore switchgear, without a significant technical failure along the route.

Everything written into this first connection becomes the template. The next project in the pipeline will follow the route this one proved, paving the way for the whole Polish industry, as the operator said.

Hugo Rojas
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.

Hugo_writer
Hugo Rojas

Hugo is an engineer with strong technical expertise. Multilingual from an early age, his writing combines technical clarity with a strong interest in science and energy.